Fort Bend County Precinct 1 Shares July 2025 Transportation Project Updates Covering Local Roads and Grand Parkway Expansion
Fort Bend County Precinct 1 is undergoing a wave of transportation improvements that promise to reshape how residents get to work, school, and home. On July 15, 2025, Commissioner Vincent Morales shared a detailed progress report on road, sidewalk, drainage, and Grand Parkway projects designed to keep up with the county’s rapid growth. These updates aren’t just about pouring concrete and laying asphalt—they represent planning for safer intersections, smoother commutes, and improved quality of life for families in Woodcreek Reserve and throughout the precinct.
Key Roadway and Drainage Projects
Skinner Lane (Segments 1–4)
-
Segment 1 (W. Bellfort to north of McCrary Rd): Survey and geotechnical work are complete. Alignment adjustments are being made to address drainage and limited right-of-way, with underground drainage and curb-and-gutter options under consideration.
-
Segment 2 (Drainage & Utility Coordination): A drainage study is ongoing, focused on in-line detention and utilizing excess right-of-way for stormwater storage. Environmental reviews may be needed due to wetlands impacts.
-
Segment 3 (north of McCrary Rd to Brandt Rd): Survey and geotechnical work are finished. Drainage design will include channel alignment and small detention areas within excess right-of-way.
- Segment 4 (Brandt Rd to Mason Rd): Alignment studies continue, with environmental impacts from wetlands under review. To protect these areas, roadway curvature may be reduced, resulting in a lower speed limit (from 40 mph to 35 mph).
Pool Hill Road (Segments 1–3)
All three segments are in various stages of alignment and drainage design. Survey and geotechnical fieldwork are largely complete, with upcoming meetings to coordinate roadway alignment and drainage integration. Right-of-way acquisition is anticipated, primarily along the west side of segment one and both sides of segment three.
Hunt Road (Segments 1–3)
-
Segment 1 (1900’ W of FM 359 to FM 359): A drainage study is in progress to identify future detention solutions, with right-of-way needs on the north side of Bessie Creek. Survey and geotechnical investigations are complete.
-
Segment 2 (5225’ W of FM 359 to 1900’ W of FM 359): Final alignment review is underway, with right-of-way anticipated primarily on the south side. TxDOT bridge replacements are being coordinated.
-
Segment 3 (1800’ W of Pool Hill Rd to 5225’ W of FM 359): Alignment and bridge planning are underway, including a second bridge to match TxDOT’s program and anticipated construction cost increases.
Fulshear Bend Drive
Survey and geotechnical work have begun, with alignment coordination planned for the new TxDOT signal at FM 359. Discussions with area developers are ongoing to determine final tie-in locations and phasing.
Sidewalk Improvements (Various Locations)
Funding approval is in progress, with Katy Gaston identified as the first location. Survey work will help refine design concepts and cross-slope data before moving to the legal phase.
Mobile Sidebar Ad
Ongoing Construction and Right-of-Way Acquisitions
Stella Road
Phase 1 is complete, and traffic has shifted to Phase 2. The project is nearing final completion, projected for October 2025.
Wallis Street (FM 1093 to FM 359)
Thirty-five parcels are under acquisition, with 26 closed and nine in eminent domain. Intersection design options at FM 1093 are being evaluated.
Bowser Road (Winding Stream Dr. to Pool Hill Rd)
All 39 parcels are in acquisition, with TxDOT permits under review. Detention pond sizing is being coordinated to minimize frontage impacts.
Boothill Bypass (Simonton)
Final design is complete, and land acquisition is ongoing, including utility relocation costs submitted for approval.
Fulshear Gaston Road (Phases 1 & 2)
Drainage, traffic control, and parcel acquisitions are progressing, including easement revisions due to survey updates and pipeline coordination.
Traffic Signals and Safety Improvements
New intersection safety projects are in design, including multiple signalized intersections and traffic control enhancements.
Settegast Ranch Road (Segments 1 & 2)
Plans call for upgrading two-lane asphalt roads to four-lane boulevards with storm sewers and traffic signals. Additional drainage analysis and right-of-way adjustments are underway.
Falcon Landing Boulevard
A new westbound right-turn lane is planned, requiring no additional right-of-way.
Rogers Road (Segments 1 & 2)
Both segments will expand to four-lane boulevards, with right-of-way needs on the north side and sidewalk integration into FM 359 tie-ins.
Other Projects
Additional projects include sidewalk expansions, traffic signal installations at Cinco Ranch Boulevard, and new access roads for Ginter Library.
Grand Parkway (Highway 99) Updates
Grand Parkway frontage road and mainlane projects are a major component of the July 2025 update:
-
Construction Progress: The southbound frontage road between Westheimer and Cinco Ranch and from FM 1093 to Fry Road is under construction, with substantial completion anticipated by summer 2025.
-
Future Lettings (2026): Multiple design packages covering northbound and southbound frontage roads and mainlane widenings are scheduled for letting between March and September 2026. The county has requested bundling these into three packages to accelerate timelines.
-
Drainage & Utility Coordination: Final drainage reports and right-of-way documents are being reviewed. Noise studies and public workshops are planned for fall 2025.
- Community Engagement & Land Acquisition: Meetings with HOAs and community stakeholders, including Falcon Point and Grand Lakes, are ongoing. Voting on key property sales to Fort Bend County is expected to conclude by July 27, 2025.
Mobile Sidebar Ad
Commissioner Morales on Infrastructure Commitment
Commissioner Vincent Morales emphasized the importance of these investments for residents, noting that “drainage and safety considerations are central to every alignment decision we make.” He explained that the county is “coordinating with developers and TxDOT to ensure these projects meet both current and future mobility needs.”
Morales also highlighted the role of local input, stating, “residents’ feedback is critical in shaping how these projects move forward.” He concluded by reaffirming the goal of these improvements: “our focus is on delivering infrastructure improvements that make daily commutes safer and more efficient.”
What It Means for Woodcreek Reserve Residents
For Woodcreek Reserve residents who often feel the daily frustration of traffic delays or worry about flooding during heavy rains, these projects offer hope and real change on the horizon. As Commissioner Morales noted, these efforts are about more than building roads—they are about creating a stronger, safer community for everyone who calls Precinct 1 home. With multiple projects already under construction and more scheduled in the coming year, residents can expect to see these improvements making an impact soon.
Stay tuned with My Neighborhood News for ongoing coverage of Fort Bend County Precinct 1 infrastructure improvements and public engagement opportunities.