Elgin Forward Project Reaches Major Drainage Milestone Near Homestead Estates
For Homestead Estates residents who regularly travel County Line Road or nearby streets, the construction detours and changing traffic patterns are part of a larger effort to reduce flooding and improve long-term mobility in the area.
The City of Elgin’s latest Elgin Forward project update, released July 10, shows substantial progress on the County Line Road Phase II and Kennedy Street Flood Mitigation projects. Approximately 1,450 linear feet of reinforced concrete storm drain box have now been installed, creating the core of the new drainage system designed to move stormwater away from flood-prone areas more effectively.
Major closures have remained in place on County Line Road and Kennedy Street since late April. While the work continues to affect daily travel, the latest update provides a clearer look at what crews have completed beneath the roadways and what still needs to happen before paving begins.
Drainage System Takes Shape Along County Line Road and Kennedy Street
Contractor Larry Young Paving has continued working through utility relocations, heavy rainfall and difficult clay-heavy soil conditions.
Along the approximately 2,700-foot County Line Road corridor, the project will include roadway widening and new sidewalks in addition to drainage improvements. Crews are now preparing and stabilizing the roadway subgrade, which forms the foundation beneath the future pavement.
Work is also advancing near Kennedy Street and Central Avenue. The stormwater retention pond has been excavated, and a new concrete drainage structure has been installed across Central Avenue.
These improvements are intended to help reduce repetitive flooding, improve stormwater drainage and create safer, more accessible travel routes as Elgin continues to grow.
Recent Rainfall Slows Work but Construction Continues
Recent storms have created additional challenges at the construction sites. Saturated clay soil can be difficult to stabilize, and crews have needed to remove standing water before some work can continue.
The stormwater retention facility has required additional dewatering efforts following the rain. Despite those delays, the City reported that construction continues to move forward on both streets.
A City inspector remains on-site throughout the project to verify that materials, drainage structures and roadway improvements meet the required construction specifications.
What Homestead Estates Residents Should Know About Road Closures
County Line Road remains closed farther south than it was during the project’s earlier stages. The closure was extended from Briar Brush Lane to a point just south of Bandara Woods Boulevard so crews could complete storm drain connections and roadway expansion work.
Drivers should continue watching for construction signage and allow additional travel time when using County Line Road, FM 1100 or nearby alternate routes.
The City has also been sequencing closures around Kennedy Street, Central Avenue and West Brenham Street to preserve at least one east-west route through the area whenever possible. Because active construction conditions can change, Homestead Estates residents should confirm their route before traveling through the work zone.
The City previously said it would work with services including Google Maps, Apple Maps, Waze and 511 to reflect construction information, though navigation applications may not update immediately.
Nearly $11 Million Grant Supports Flood Mitigation Work
The Elgin Forward project is funded through a $10,940,981 Community Development Block Grant–Mitigation award from the Texas General Land Office, supplemented by developer fees. City information indicates that the project is not expected to place an additional financial burden on local taxpayers.
The funding is part of a broader $28 million infrastructure investment in Bastrop County focused on reducing flood risks in low- to moderate-income areas.
Altogether, the project includes approximately 4,639 linear feet of improvements along County Line Road, Kennedy Street, Central Avenue and Brenham Road. Planned work includes storm sewer replacement, culvert installation, roadway widening, sidewalks, curbs and gutters, drainage ditch regrading and limited tree removal where necessary.
Why the Elgin Forward Project Matters Locally
For nearby neighborhoods, the project is about more than rebuilding sections of roadway. Improved drainage could help protect homes, streets and neighborhood access during heavy rainfall, while wider roads and new sidewalks are expected to improve safety for drivers and pedestrians.
The work may also strengthen the reliability of routes that families use to reach schools, businesses, downtown Elgin and major roads connecting the community to the surrounding region.
Construction began April 27, 2026, and the City currently lists December 31, 2026, as the anticipated completion date. Weather, utility conflicts and ground conditions could continue to affect the schedule.
Residents with questions about the Elgin Forward County Line Road and Kennedy Street projects may contact Elgin Public Information Officer Stacey Ford Osborne at Stacey.osborne@elgintexas.gov.
Stay tuned to My Neighborhood News for additional construction updates affecting Homestead Estates and the surrounding Elgin community.