Contact Our Team
Find Your Community 1952812B-4B04-4F26-B0D2-242933E81916
 
Water Well Tests in Hearthstone

Water Well Tests in Hearthstone

March 27 2023

The message below was sent to Hearthstone residents from Katie Ivanics with Inframark on Monday, March 27, 2023.

Dear Residents:

Starting March 28, there will be pump testing being conducted. Well development can be noisy and the pump tests will be noisy/lengthy.

The contractor will be doing two types of tests. The first one is a step test where they pump 3 hours, then rest 3 hours, doing this four times.  The second test involves a continuous 36 hours of pumping. 

  1. Starting Tuesday, 3/28 at 7:00 AM,  the first step test will kick off.  Pumping will be on and off all day and night.
  2. The last step test will be from 1:00 AM - 4:00 AM in the morning of Wednesday, 3/29.
  3. The 36-hr test will start Wednesday, 3/29 at 10:00 PM and run until Friday, 3/31 at 10:00 AM.
 




LATEST WEST HOUSTON / CYPRESS NEWS

Subscribe to Your
West Houston / Cypress
Newsletter

Stay current on local news and events with periodic emails sent straight to you!

Select Your Region/Community