The message below was sent to Hearthstone residents from Katie Ivanics with Inframark on Monday, March 27, 2023.

Dear Residents:

Starting March 28, there will be pump testing being conducted. Well development can be noisy and the pump tests will be noisy/lengthy.

The contractor will be doing two types of tests. The first one is a step test where they pump 3 hours, then rest 3 hours, doing this four times.  The second test involves a continuous 36 hours of pumping. 

  1. Starting Tuesday, 3/28 at 7:00 AM,  the first step test will kick off.  Pumping will be on and off all day and night.
  2. The last step test will be from 1:00 AM - 4:00 AM in the morning of Wednesday, 3/29.
  3. The 36-hr test will start Wednesday, 3/29 at 10:00 PM and run until Friday, 3/31 at 10:00 AM.
 


Find out more about Sield-Bearer Counseling

LATEST WEST HOUSTON / CYPRESS NEWS

Subscribe to Your
West Houston / Cypress
Newsletter

Stay current on local news and events with periodic emails sent straight to you!

Select Your Region/Community