South Lamar Construction Plans: Austin Hosts December 2 Open House Ahead of 2027 Work
For Austin residents who rely on South Lamar Boulevard to get to work, shop or catch a bus, a December 2 community open house offers a chance to see how planned construction could affect those everyday trips. Austin Transportation and Public Works has completed the final design for improvements between Barton Springs Road and U.S. 290, with the first major construction segment expected to begin in early 2027.
When and Where to Attend
The drop-in open house will take place Wednesday, December 2, 2026, from 5 to 7 p.m. in the Bluewillow Lounge at Wheatsville Co-op, 4001 South Lamar Boulevard. Visitors can examine maps, discuss access concerns with the project team and explain how their travel or business operations might be affected.
What Is Changing Along South Lamar?
Supported by the 2016 Mobility Bond, the project combines transportation improvements with infrastructure renewal. Plans include accessible walking routes, bicycle lanes, crossing upgrades, intersection improvements and pavement resurfacing. A northbound lane giving priority to transit is planned between Barton Skyway and Menchaca Road. Drainage work, rain gardens, water and wastewater upgrades and landscaping are also included, with improvements varying by location.
Construction Timeline and Changes to the Original Plans
Work is divided at Montclaire Street. The southern section extending to U.S. 290 is expected to start in early 2027, following the September 24 bid deadline. The northern section extending to Barton Springs Road is in permitting, with bidding anticipated in 2029 and construction tentatively scheduled for 2030. These dates may change.
The Mary Street roundabout was completed in spring 2026. The Del Curto Road and Bluebonnet Lane roundabout is anticipated in fall 2027 as part of drainage construction. The previously considered section north of Barton Springs Road toward Riverside Drive is excluded from the current project. A proposed Treadwell Street connection was also removed after Union Pacific Railroad declined both crossing proposals.
What Residents and Businesses Can Expect
The city plans to keep driveways accessible throughout construction, although drivers should prepare for lane restrictions and shifting traffic patterns. People traveling on foot may encounter detours, and the city is working with CapMetro on bus stop changes.
Residents can subscribe to construction notices through the official South Lamar Boulevard Corridor project page or contact the team at AustinMobilityBonds@AustinTexas.gov or 512-974-2300.
Johnny Krenek has been connected to community news since childhood, growing up alongside the family business his parents founded—Krenek Printing. Today, he serves as Vice President and lead developer for My Neighborhood News, where he drives the digital experience and supports the team across a variety of technical and operational roles. He is passionate about building tools that help connect neighbors and strengthen communities.