San Antonio Outlines $14.6 Million Bulverde Road Phase II Improvements From Green Spring Drive to Redland Road
Bulverde Road Phase II calls for $14.6 million in corridor improvements between Green Spring Drive and Redland Road in San Antonio. The city's 2022-2027 bond project page lists Bulverde Road Phase II in the design phase as of November 25, 2026, with an estimated construction window extending into 2028.
The project calls for roadway improvements, sidewalks, curbs, driveway approaches, drainage and bicycle facilities, along with other improvements where applicable and within available funding.
How Bulverde Road Phase II Is Funded
The City of San Antonio's official Bulverde Road Phase II project page lists a total budget of $14,615,257.13. Of that amount, $13 million comes from the city's 2022 General Obligation Bond for streets, while Bexar County is contributing $1,615,257.13.
Phase II covers Green Spring Drive to Redland Road. It is part of a multi-phase effort, but is separate from Bulverde Road Phase I, which covers Butterleigh Drive to north of Quiet Meadow Street.
When Is Bulverde Road Phase II Construction Expected?
San Antonio lists fall 2026 through summer 2028 as the estimated construction timeline. Under the city's published seasonal definitions, fall covers October through December and summer covers July through September. The dates are estimates, and the project remains listed as being in design. The project page does not establish that construction has begun or identify confirmed lane closures or detours.
How Residents and Businesses Can Follow the Project
Residents can sign up for project updates and information about future public meetings through SASpeakUp, where the city also accepts questions and feedback. Project contact Katherine Schneider can be reached at 210-207-8549 or katherine.schneider3@sanantonio.gov.
The project page also links to San Antonio's Construction Toolkit, available in English and Spanish, to help businesses prepare for city construction projects, and to the city's construction dashboards.
Johnny Krenek has been connected to community news since childhood, growing up alongside the family business his parents founded—Krenek Printing. Today, he serves as Vice President and lead developer for My Neighborhood News, where he drives the digital experience and supports the team across a variety of technical and operational roles. He is passionate about building tools that help connect neighbors and strengthen communities.