Magnolia ISD High School Additions Follow Board's Approval of Construction-Management Contracts
AI-generated illustration; not Magnolia ISD facilities or proposed designs.

Magnolia ISD High School Additions Follow Board's Approval of Construction-Management Contracts

Magnolia Springs  /   North Houston
November 25 2026

Magnolia ISD's 2026 bond program includes additions at both of its existing high schools as well as construction of a third high school. Families following those investments can trace a key decision to September 14, 2026, when the Board of Trustees approved construction-management contracts for all three projects. More recently, the November 16 board meeting agenda listed a design review for the high school additions.

What Magnolia ISD Trustees Authorized in September

Trustees approved contracts with Stewart Builders Inc., as recorded in the approved September 14 meeting minutes, for High School No. 3 and additions to Magnolia High School and Magnolia West High School. Trustee Quinn Tolbert made the motion, Dacia Owens seconded it, and all seven trustees voted in favor.

The authorization included an owner and construction manager at risk (CMAR) agreement, general conditions for the construction contracts and a prevailing wage rate exhibit. A CMAR arrangement brings a construction manager into the project delivery process to coordinate construction planning and execution. The approved minutes do not specify a guaranteed maximum price or construction start date for the additions.

How the High School Projects Fit Into Magnolia ISD's 2026 Bond

Magnolia ISD voters approved the $465,688,326 bond proposition on May 2, 2026, with 63% support, according to the district's May 5 announcement. Approximately 92% of the bond funding is dedicated to facilities.

While the additions are investments in Magnolia High School and Magnolia West High School, the new High School No. 3 is a separate campus planned along FM 1486. In May, the district projected a 2030 opening for the third high school and 2028 and 2029 openings for Elementary Schools No. 10 and No. 11, respectively. Those projections are for new campuses, not completion dates for the existing high school additions.

Find out more about My Neighborhood News

Following the High School Additions Design Review

The November 16 board agenda listed a high school additions design review under the superintendent's report, item 7.A. That item was scheduled as a report, separate from the construction-management contracts approved in September.


By Johnny Krenek, My Neighborhood News 
Johnny Krenek, authorJohnny Krenek has been connected to community news since childhood, growing up alongside the family business his parents founded—Krenek Printing. Today, he serves as Vice President and lead developer for My Neighborhood News, where he drives the digital experience and supports the team across a variety of technical and operational roles. He is passionate about building tools that help connect neighbors and strengthen communities.

Browse the Magnolia Springs neighborhood business directory. Add your business or recommend a favorite.

LATEST NORTH HOUSTON NEWS

SUBSCRIBE

Subscribe to Your
Tavola West
Newsletter

Stay current on local news and events with periodic emails sent straight to you!